Update progress


14 July 2022

Recently we have made great steps in the executing phase of the project, namely the construction of the drilling site.

This is what has happened:

  • Scaffolding set up for making soil-displacing* piles
  • Freeing the poles
  • Dismantling the scaffolding for making the soil-displacing* piles
  • Disposal of the remaining batch of soil

In the near future, sand and repak (soil with broken rubble in it) will be brought to the site. This will then be used to fill up and level the ground. This is necessary for the proper installation of the foundation and later the concrete.

*soil displacement piles are piles that are drilled into the ground for the strength of the ground and to prevent vibrations.