The following activities were carried out last week:
Over the next few days, containers will be placed in the parking garage next to the GTD location. Subsequently, an auxiliary steel construction will also be installed next week. The containers and steel construction are necessary for the installation of the noise barriers. The sound barriers will actually be installed from 12 June.
In weeks 23 and 24, the noise monitoring and vibration meters will be installed, the containers will be delivered for the drilling crew and the purchasing station will be connected to the drilling rig by Stedin.