Update construction week 22


1 June 2023

The following activities were carried out last week:

  • The installation and connection of water pipes and construction power at the location.
  • Installing the entry and exit ramp from the drilling site to the Leeghwaterstraat.
  • Assembly work on and on the derrick.

Over the next few days, containers will be placed in the parking garage next to the GTD location. Subsequently, an auxiliary steel construction will also be installed next week. The containers and steel construction are necessary for the installation of the noise barriers. The sound barriers will actually be installed from 12 June.

In weeks 23 and 24, the noise monitoring and vibration meters will be installed, the containers will be delivered for the drilling crew and the purchasing station will be connected to the drilling rig by Stedin.

Tags
Construction
2024 © Knijnenburg Producties