Update construction week 21


25 May 2023

We've been working hard this past week! 

  • The derrick has been delivered and placed at the drilling location.
  • Fencing and lighting is placed around the laydown area.
  • From tomorrow on, the Leeghwaterstraat will be closed until after the drilling. Signs have been installed for car traffic, cyclists and pedestrians.

Next week a temporary passage will be made from the drilling location to the lay-down area. The installation of the construction on the parking garage that is necessary for installing the noise barriers will also start.

Timelapse placing derrick crane.