Update construction February


7 February 2023

What work has been carried out recently? 

  • Installation of sound meters
  • Installation and sealing of two conductor pipes (these pipes will house the well)  
  • Installation of Stedin procurement station (a procurement station provides a connection to the electricity grid and distributes it to the transformer stations)
  • Site clearance work 

The work of phase 1 (construction of the drilling site) is almost complete. In the coming period, there are still some remaining works, such as sealing the well cellars around the conductor pipes, sealing the gutters and placing the covers of the clean water well. The clean water well is a large container in the ground where rainwater enters via a system of gutters during a rainstorm. 

Otherwise, there will be little to no work in the coming period. As soon as the construction of the bore gets closer (April), we will resume work and there will be new updates on the website.