First construction activities on the Geothermal Delft site


22 June 2022

Over the past few weeks, the first construction activities have begun on the construction site. We are working hard on phase 1 of the project!

What has happened so far?

  • Construction entrance and exit
  • Placing construction canvases and fences with sound-absorbing cladding
  • Excavation and removal of soil
  • Installation of electricity and water connection on the construction site

In the coming period, the foundation work for the above-ground building and the drilling rig will be done. The foundation is done with screw piles so that pile driving is not necessary. The piles will now be rotated into the ground. This will produce virtually no noise and therefore no nuisance is expected. The pile work is expected to take approximately three weeks.

Would you like to be kept informed of all developments around Geothermics Delft? Then sign up for the newsletter.