Construction update week 23


12 June 2023

The following activities were carried out last week:

  • Installing of an auxiliary steel structure and containers on the parking garage that are necessary for the installation of the noise barriers
  • Installing of the water pipe and construction flow around the drilling site and construction area
  • The containers for the drilling crew are supplied. These include offices and accommodation for the drilling crew, who will soon be on site 24 hours a day, seven days a week
  • Assembly work on and on the derrick

This week, the noise barriers on the thatched auxiliary construction in the parking garage will be placed and the noise monitoring and vibration measurements will be installed. In addition, in the preceding two weeks, the cables will be connected from the procurement station, after which the procurement station will be commissioned and additional equipment will be delivered.

Testing of the derrick will start in the week of June 19. No drilling will take place at this time, the testing is solely intended to check that all equipment of the drilling rig is functioning for the possible drilling. The starting date for drilling is June 26.